Adams
					
						Genesis Rail Services LLC, Natchez Terminal, Natchez, MS  applied for a modification to their Air Synthetic Minor Operating Permit (SMOP) on 10/14/2025.
					 
				 | 
	
		| 
					
					 
						Tracetown Shopping Center, Natchez, MS  was granted a new constuction general permit coverage on 10/09/2025.
					 
				 | 
	
		| 
					
					 
						Willow Creek Management LLC, Natchez, MS  applied for renewal of their surface water discharge permit (NPDES) on 10/23/2025.
					 
				 | 
	
		
					
 Alcorn
					
						Corinth POTW, Corinth, MS  was issued a modification to their surface water discharge permit (NPDES) on 10/14/2025.
					 
				 | 
	
		
					
 Attala
					
						Attala Steel Industries LLC, Kosciusko, MS  applied for renewal of their Water State Operating Permit (SOP) on 10/20/2025.
					 
				 | 
	
		
					
 Bolivar
					
						McCreary Flying Service LLC, Alligator, MS  was issued a renewal of their Water State Operating Permit (SOP) on 10/10/2025.
					 
				 | 
	
		
					
 Clarke
					
						Stonewall POTW, Stonewall, MS  was issued a renewal of their surface water discharge permit (NPDES) on 10/16/2025.
					 
				 | 
	
		
					
 Copiah
					
						Central MS Rubbish LLC, Central MS Rubbish Class I Rubbish, Crystal Springs, MS  was granted a modification to their baseline general permit coverage on 10/13/2025.
					 
				 | 
	
		
					
 Covington
					
						MDOT, Covington, 109363 301000, Collins, MS  applied for a new constuction general permit coverage on 10/08/2025.
					 
				 | 
	
		| 
					
					 
						MDOT, Covington, 109363 301000, Collins, MS  was granted a new constuction general permit coverage on 10/29/2025.
					 
				 | 
	
		| 
					
					 
						TransMontaigne Operating Company LP, Collins Southeast Terminal, Collins, MS  applied for renewal of their Air Synthetic Minor Operating Permit (SMOP) on 10/06/2025.
					 
				 | 
	
		
					
 Desoto
					
						BCC, LLC, Willow Creek Estates, Olive Branch, MS  applied for a new constuction general permit coverage on 10/20/2025.
					 
				 | 
	
		| 
					
					 
						Bridgforth Properties, Bridgforth Road Estates, Olive Branch, MS  was granted a new constuction general permit coverage on 10/09/2025.
					 
				 | 
	
		| 
					
					 
						ChrisJon Development, LLC, Rosewood, Olive Branch, MS  was granted a new constuction general permit coverage on 10/09/2025.
					 
				 | 
	
		| 
					
					 
						Forest Hill Community, Olive Branch, MS  was granted a modification to their construction general permit coverage on 10/09/2025.
					 
				 | 
	
		| 
					
					 
						Laney Funderbunk Family, LP, The Preserve Subdivision, Hernando, MS  was granted a new constuction general permit coverage on 10/08/2025.
					 
				 | 
	
		| 
					
					 
						MZX Tech LLC, Southaven, MS  was granted a new constuction general permit coverage on 10/10/2025.
					 
				 | 
	
		| 
					
					 
						Overland Contracting Inc, Entergy Penton Solar Photovoltaic Generating Facility Project, Lake Cormorant, MS  applied for a new constuction general permit coverage on 10/07/2025.
					 
				 | 
	
		| 
					
					 
						Rankin First Economic Development Authority, West Rankin Industrial Park, Site Clearing, Pearl, MS  applied for a new constuction general permit coverage on 10/28/2025.
					 
				 | 
	
		| 
					
					 
						Southbranch Development, LLC, Villages at Southbranch, Olive Branch, MS  applied for a modification to their construction general permit coverage on 10/24/2025.
					 
				 | 
	
		| 
					
					 
						Yaser Saleh Sal Krown Investment, LLC,Progress Way, Hacks Cross Road Truck Stop, Olive Branch, MS  was granted a new constuction general permit coverage on 10/07/2025.
					 
				 | 
	
		
					
 Forrest
					
						98 Waste and Recycling, LLC, 98 Waste Class I Rubbish Disposal Site, Hattiesburg, MS  was granted a new baseline general permit coverage on 10/06/2025.
					 
				 | 
	
		| 
					
					 
						Camp Shelby Joint Forces Training Center, Lake Janney Wet Gap Project, Camp Shelby, MS  was granted a new constuction general permit coverage on 10/10/2025.
					 
				 | 
	
		| 
					
					 
						Camp Shelby Joint Forces Training Center, Lake Janney Wet Gap Project, Camp Shelby, MS  was issued a Water Quality 401 Certification on 10/17/2025.
					 
				 | 
	
		| 
					
					 
						Great River Utility Operating Company LLC, Reese Creek Lagoon, Petal, MS  was issued a renewal of their surface water discharge permit (NPDES) on 10/14/2025.
					 
				 | 
	
		
					
 Greene
					
						Mississippi Department of Corrections, South Mississippi Correctional Institution, Leakesville, MS  applied for renewal of their surface water discharge permit (NPDES) on 10/20/2025.
					 
				 | 
	
		
					
 Harrison
					
						Gulf Coast 7th Day Adventist Church, Biloxi, MS  was issued a renewal of their surface water discharge permit (NPDES) on 10/24/2025.
					 
				 | 
	
		| 
					
					 
						Ports America, West Pier Parking Area, Gulfport, MS  was granted a new constuction general permit coverage on 10/22/2025.
					 
				 | 
	
		
					
 Hinds
					
						Cintas Corporation, Jackson, MS  applied for renewal of their water pretreatment permit on 10/08/2025.
					 
				 | 
	
		| 
					
					 
						Dyas Construction, Inc, UPS Jackson Mississippi, Jackson, MS  was granted a new constuction general permit coverage on 10/28/2025.
					 
				 | 
	
		| 
					
					 
						Entergy Corporation, South Utica 6Y03, Utica, MS  was granted a modification to their construction general permit coverage on 10/17/2025.
					 
				 | 
	
		| 
					
					 
						Hinds County Economic Development Authority, Delphi Site, Clinton Substation, Clinton, MS  was granted a new constuction general permit coverage on 10/07/2025.
					 
				 | 
	
		| 
					
					 
						Jordan Estates, Jackson, MS  applied for a new constuction general permit coverage on 10/09/2025.
					 
				 | 
	
		
					
 Humphreys
					
						Catfish Processors LLC, Belzoni, MS  was issued a renewal of their surface water discharge permit (NPDES) on 10/14/2025.
					 
				 | 
	
		
					
 Jackson
					
						Chevron USA Inc, Chevron Products Company, Pascagoula Refinery, Pascagoula, MS  applied for a air construction permit on 10/16/2025.
					 
				 | 
	
		| 
					
					 
						Grantman MS, LLC, Creekwood Subdivision, St. Martin, MS  applied for a new constuction general permit coverage on 10/05/2025.
					 
				 | 
	
		| 
					
					 
						Pavco Industries Inc, Stillwater RV Resort, Pascagoula, MS  applied for a new constuction general permit coverage on 10/27/2025.
					 
				 | 
	
		| 
					
					 
						SL Coastal LLC, Crane Landing Subdivision, Ocean Springs, MS  applied for a modification to their construction general permit coverage on 10/09/2025.
					 
				 | 
	
		| 
					
					 
						Sawgrass Development, LLC, BNOS Multi-Family Subdivision, Ocean Springs, MS  applied for a new constuction general permit coverage on 10/27/2025.
					 
				 | 
	
		
					
 Jones
					
						Patterson Farms LLC, Moselle, MS  was granted a new Poultry AFO general permit coverage on 10/27/2025.
					 
				 | 
	
		
					
 Lafayette
					
						Heritage Properties Inc, Finn, Oxford, MS  applied for a new constuction general permit coverage on 10/23/2025.
					 
				 | 
	
		| 
					
					 
						LCD Acquisitions, LLC, The Station At Oxford, Oxford, MS  was granted a new constuction general permit coverage on 10/22/2025.
					 
				 | 
	
		| 
					
					 
						Walker and Walker Enterprises LLC, Walnut Grove, Oxford, MS  applied for a new constuction general permit coverage on 10/14/2025.
					 
				 | 
	
		
					
 Lamar
					
						Bass Memorial Academy, Adventist Health Center, Lumberton, MS  was issued a renewal of their surface water discharge permit (NPDES) on 10/16/2025.
					 
				 | 
	
		
					
 Lauderdale
					
						Collinsville Water Association Inc, Collinsville Shopping Center and Subdivision, Collinsville, MS  applied for renewal of their surface water discharge permit (NPDES) on 10/15/2025.
					 
				 | 
	
		| 
					
					 
						Jason Wiggins Mobile Home Park, Meridian, MS  applied for renewal of their Water State Operating Permit (SOP) on 10/09/2025.
					 
				 | 
	
		| 
					
					 
						Jason Wiggins Mobile Home Park, Meridian, MS  was issued a renewal of their Water State Operating Permit (SOP) on 10/24/2025.
					 
				 | 
	
		| 
					
					 
						QuikTrip Corporation, QuikTrip 7257, Meridian, MS  was granted a new constuction general permit coverage on 10/06/2025.
					 
				 | 
	
		
					
 Lawrence
					
						Georgia Pacific Monticello LLC, Monticello, MS  applied for a modification to their construction general permit coverage on 10/06/2025.
					 
				 | 
	
		
					
 Lee
					
						Grammer Inc, Shannon, MS  applied for a new constuction general permit coverage on 10/08/2025.
					 
				 | 
	
		| 
					
					 
						H M Richards Inc, Guntown, MS  applied for a modification to their Air Synthetic Minor Operating Permit (SMOP) on 10/13/2025.
					 
				 | 
	
		| 
					
					 
						MTD Products Company, Verona, MS  was issued a renewal of their water pretreatment permit on 10/06/2025.
					 
				 | 
	
		| 
					
					 
						Scruggs Commons Subdivision, Saltillo, MS  applied for a modification to their construction general permit coverage on 10/31/2025.
					 
				 | 
	
		| 
					
					 
						Tecumseh Compressor Company, Verona, MS  was issued a renewal of their water pretreatment permit on 10/06/2025.
					 
				 | 
	
		
					
 Leflore
					
						Leflore County Board of Supervisors, Leflore County Municipal Solid Waste Landfill, Sidon, MS  applied for a modification to their solid waste municipal landfill permit on 10/20/2025.
					 
				 | 
	
		
					
 Lincoln
					
						Miskelly Farm LLC, Ruth, MS  was granted a new constuction general permit coverage on 10/06/2025.
					 
				 | 
	
		| 
					
					 
						Miskelly Farm LLC, Ruth, MS  was granted a new Poultry AFO general permit coverage on 10/06/2025.
					 
				 | 
	
		
					
 Lowndes
					
						Aluminum Dynamics, LLC, Columbus, MS  was issued an administrative amendment to their Air Construction PSD permit on 10/08/2025.
					 
				 | 
	
		| 
					
					 
						Great River Utility Operating Company LLC, Doyle Estates Subdivision, Columbus, MS  applied for renewal of their surface water discharge permit (NPDES) on 10/07/2025.
					 
				 | 
	
		| 
					
					 
						SDI Biocarbon Solutions, LLC, Columbus, MS  was granted a new baseline general permit coverage on 10/30/2025.
					 
				 | 
	
		| 
					
					 
						Tennesse Valley Authority, TVA Lowndes, New Hamilton Project, Caledonia, MS  was granted a new constuction general permit coverage on 10/10/2025.
					 
				 | 
	
		
					
 Madison
					
						Bainbridge, Canton, MS  applied for a new constuction general permit coverage on 10/14/2025.
					 
				 | 
	
		| 
					
					 
						Birdsong Construction, County Line Substation, Ridgeland, MS  was granted a modification to their construction general permit coverage on 10/07/2025.
					 
				 | 
	
		| 
					
					 
						Entergy Mississippi LLC, Madison County Advanced Power Station, Ridgeland, MS  applied for a modification to their construction general permit coverage on 10/22/2025.
					 
				 | 
	
		| 
					
					 
						Livingston Landing, LLC, Livingston Landing Phase 1, Flora, MS  was granted a new constuction general permit coverage on 10/09/2025.
					 
				 | 
	
		| 
					
					 
						Peco Foods Inc, Canton, MS  was issued a renewal of their water pretreatment permit on 10/27/2025.
					 
				 | 
	
		| 
					
					 
						Puckett Machinery Company, Puckett Rents, Gluckstadt, MS  applied for a new constuction general permit coverage on 10/21/2025.
					 
				 | 
	
		
					
 Marion
					
						W L Burle Engineers, P A, Coxs Triangle Mini Mart, Foxworth, MS  was granted a new underground storage tanks general permit coverage on 10/08/2025.
					 
				 | 
	
		
					
 Marshall
					
						MDOT, Marshall, 106103 301000, Holly Springs, MS  applied for a new constuction general permit coverage on 10/27/2025.
					 
				 | 
	
		| 
					
					 
						Roxul USA Inc, Byhalia, MS  applied for a new constuction general permit coverage on 10/24/2025.
					 
				 | 
	
		
					
 Monroe
					
						Sterling Specialty Chemicals US LLC, Aberdeen, MS  was issued a modification to their Air Synthetic Minor Operating Permit (SMOP) on 10/17/2025.
					 
				 | 
	
		
					
 Montgomery
					
						Prestage Farms MS Inc, PM-18, Stewart, MS  was granted a renewal to their CAFO general permit coverage on 10/27/2025.
					 
				 | 
	
		| 
					
					 
						RaceTrac Inc, RaceTrac Winona, Winona, MS  was granted a new constuction general permit coverage on 10/09/2025.
					 
				 | 
	
		
					
 Newton
					
						Shane Wall, Williams Mine, Hickory, MS  was granted a new mining general permit coverage on 10/20/2025.
					 
				 | 
	
		| 
					
					 
						Terry Thai, Poultry dba T and M Farms, Union, MS  applied for a new constuction general permit coverage on 10/08/2025.
					 
				 | 
	
		| 
					
					 
						Terry Thai, Poultry dba T and M Farms, Union, MS  applied for a new Poultry AFO general permit coverage on 10/08/2025.
					 
				 | 
	
		
					
 Noxubee
					
						Kyle Mininger, Poultry dba Cedar Creek Farm, Brooksville, MS  was granted a new Poultry AFO general permit coverage on 10/27/2025.
					 
				 | 
	
		| 
					
					 
						Kyle Mininger, Poultry dba Cedar Creek Farm, Brooksville, MS  was granted a new constuction general permit coverage on 10/27/2025.
					 
				 | 
	
		| 
					
					 
						Lynn Seiler Poultry, Macon, MS  was granted a new Poultry AFO general permit coverage on 10/27/2025.
					 
				 | 
	
		| 
					
					 
						Lynn Seiler Poultry, Macon, MS  was granted a new constuction general permit coverage on 10/27/2025.
					 
				 | 
	
		| 
					
					 
						Macon Treating Company, Macon, MS  applied for renewal of their surface water discharge permit (NPDES) on 10/30/2025.
					 
				 | 
	
		| 
					
					 
						Ricky Wiebe dba Fox Chase Poultry, Macon, MS  was granted a new Poultry AFO general permit coverage on 10/27/2025.
					 
				 | 
	
		
					
 Pearl River
					
						Keet O Gary Construction, LLC, TA Travel Center Poplarville Main Street, Poplarville, MS  applied for a new constuction general permit coverage on 10/06/2025.
					 
				 | 
	
		
					
 Perry
					
						Jason S and Kelly R Edwards, dba Craz E Farms, Richton, MS  applied for a new Poultry AFO general permit coverage on 10/09/2025.
					 
				 | 
	
		| 
					
					 
						Jason S and Kelly R Edwards, dba Craz E Farms, Richton, MS  applied for a new constuction general permit coverage on 10/09/2025.
					 
				 | 
	
		
					
 Pike
					
						W L Byrd Lumber Company Inc, Fernwood, MS  was issued a renewal of their surface water discharge permit (NPDES) on 10/06/2025.
					 
				 | 
	
		| 
					
					 
						Weyerhaeuser NR Company, McComb Wood Products, Magnolia, MS  was issued a renewal of their surface water discharge permit (NPDES) on 10/09/2025.
					 
				 | 
	
		
					
 Pontotoc
					
						Ashley Furniture Industries Inc, Ecru Facility, Ecru, MS  applied for a new constuction general permit coverage on 10/16/2025.
					 
				 | 
	
		
					
 Rankin
					
						Hinds Community College, The Commons, Pearl, MS  applied for a new constuction general permit coverage on 10/23/2025.
					 
				 | 
	
		| 
					
					 
						Reservoir North, LLC, Brandon, MS  was granted a modification to their construction general permit coverage on 10/07/2025.
					 
				 | 
	
		| 
					
					 
						Vineyard Church of Jackson, Flowood, MS  applied for renewal of their Water State Operating Permit (SOP) on 10/14/2025.
					 
				 | 
	
		
					
 Scott
					
						Biloxi Beach Group Number 1, Morton, MS  applied for a water pretreatment permit on 10/21/2025.
					 
				 | 
	
		| 
					
					 
						Craig Harrell Poultry, Lena, MS  was granted a new Poultry AFO general permit coverage on 10/15/2025.
					 
				 | 
	
		| 
					
					 
						Craig Harrell Poultry, Lena, MS  was granted a new constuction general permit coverage on 10/15/2025.
					 
				 | 
	
		| 
					
					 
						Kristin and Jason Bagley Poultry, Pulaski, MS  was granted a new constuction general permit coverage on 10/27/2025.
					 
				 | 
	
		| 
					
					 
						Kristin and Jason Bagley Poultry, Pulaski, MS  was granted a new Poultry AFO general permit coverage on 10/27/2025.
					 
				 | 
	
		
					
 Smith
					
						JB3 Farms LLC, Taylorsville, MS  was granted a new constuction general permit coverage on 10/10/2025.
					 
				 | 
	
		| 
					
					 
						JB3 Farms LLC, Taylorsville, MS  was granted a new Poultry AFO general permit coverage on 10/10/2025.
					 
				 | 
	
		
					
 Sunflower
					
						Moon River Foods Inc, Indianola, MS  was issued a renewal of their surface water discharge permit (NPDES) on 10/06/2025.
					 
				 | 
	
		
					
 Tallahatchie
					
						MDOT, Tallahatchie, 102383 302000, Tutwiler, MS  applied for a new constuction general permit coverage on 10/20/2025.
					 
				 | 
	
		| 
					
					 
						SRB Aerial Applicators LLC, Charleston, MS  applied for renewal of their Water State Operating Permit (SOP) on 10/07/2025.
					 
				 | 
	
		
					
 Tippah
					
						Blue Mountain Production Company, Taylor and Plant Property Mine, Blue Mountain, MS  applied for renewal of their surface water discharge permit (NPDES) on 10/17/2025.
					 
				 | 
	
		
					
 Tishomingo
					
						Patrick Industries Inc dba Baymont Industries Plant No. 2, Belmont, MS  was issued a new Air Title V Permit on 10/07/2025.
					 
				 | 
	
		| 
					
					 
						Patrick Industries, Inc, Baymont Composites, Burnsville, MS  was issued a new Air Title V Permit on 10/07/2025.
					 
				 | 
	
		
					
 Walthall
					
						Charles Ray Polk, Poultry, Tylertown, MS  was granted a modification to their Dry Litter Poultry AFO general permit coverage on 10/15/2025.
					 
				 | 
	
		| 
					
					 
						Luke Harrison, Poultry dba Lukes Coop, Tylertown, MS  was granted a new Poultry AFO general permit coverage on 10/06/2025.
					 
				 | 
	
		| 
					
					 
						Persimmon Hill Poultry LLC, Tylertown, MS  was granted a modification to their Dry Litter Poultry AFO general permit coverage on 10/27/2025.
					 
				 | 
	
		
					
 Warren
					
						Enchanted Rock LLC, Entergy ERDC-EGUs, Vicksburg, MS  was issued a new Air Synthetic Minor Operating Permit (SMOP) on 10/30/2025.
					 
				 | 
	
		| 
					
					 
						Entergy Mississippi LLC, Baxter Wilson Plant, Vicksburg, MS  was granted a new hydrostatic general permit coverage on 10/30/2025.
					 
				 | 
	
		
					
 Washington
					
						MacroSource LLC, Greenville North, Greenville, MS  was issued a renewal of their Air Synthetic Minor Operating Permit (SMOP) on 10/13/2025.
					 
				 | 
	
		| 
					
					 
						Richard Baughn Construction, Inc, Greer Solar Switch Station, Hollandale, MS  was granted a new constuction general permit coverage on 10/27/2025.
					 
				 | 
	
		
					
 Wayne
					
						Ballard Contractors, Inc, Hood Industries, Waynesboro, MS  was granted a new ready mix general permit coverage on 10/15/2025.
					 
				 | 
	
		| 
					
					 
						Hood Industries Inc, Waynesboro, Waynesboro, MS  was issued a new air construction PSD permit on 10/16/2025.
					 
				 | 
	
		
					
 Winston
					
						Louisville, City of, South Industrial Road Construction, Louisville, MS  applied for a new constuction general permit coverage on 10/14/2025.
					 
				 |